Closeout Sprint Protocol
The closeout sprint trigger, deliverables, and exit gate for residential HPWH modelling projects.
The closeout sprint is the final phase of a residential modelling project. It begins when submissions are complete or when all final client-facing deliverables have been sent.
Trigger
The closeout sprint begins on the earlier of:
- All target scheme submissions are confirmed lodged; or
- EnergyAE’s scoped deliverables are complete and any client-managed lodgement has been handed over in writing.
Once triggered, the project stays active until the closeout checklist is signed off.
Closeout deliverables
1. Submission and approval records
- CER, VEU, and ESS submission confirmations saved
- Application IDs recorded in Monday.com and EMO
- Approval emails and portal screenshots saved when received
2. Client communication
- Submission confirmation sent
- Closeout email sent where useful
- Client advised to forward any regulator RFI or approval correspondence received after closeout
3. Monday.com and EMO
- Monday.com item moved to closed
- EMO updated with final certificate quantities, submission dates, approval dates, and application IDs
4. SharePoint cleanup
- Final AS/NZS 4234 report, audit packs, declarations, certificates, and submission confirmations saved in the final folders
- Working files archived
- TRNSYS tool labelled with the final version
5. Final invoice
- Final invoice issued through Xero
- Any out-of-scope work or additional applications included
6. Debrief and KMS updates
- Debrief completed within 2 weeks of final submission confirmation
- Lessons converted into KMS update tasks with an owner and target date
Exit gate
The closeout sprint exits when the director signs off the closeout checklist.
Next, complete the Post-Project Debrief.